Investment project for the construction
of a network of LNG plants
Stage I
01 July 2023 - 01 April 2024
* Construction of an LNG plant with a capacity of 6.0 tph (tons per hour)
* Supplementary exploration of the Dublikanskaya and Soloniyskaya structures with the aim of increasing the raw material base for the construction of the second stage of LNG plants with a total capacity of 18.0 tph (tons per hour)
Stage II
April 01, 2024 - November 01, 2026
* Construction of LNG plants with a total capacity of 18.0 tph tons per hour
* Production of ISO tanks
* Supplementary exploration of the Alekandrovskaya and Urgalskaya structures with the aim of increasing the gas reserves for the construction of the third stage of LNG plants with a total capacity of 36.0 tph tons per hour
Stage III
December 01, 2026 - July 01, 2028
* Construction of LNG plants with a total capacity of 36.0 tph tons per hour
* Production of an additional number of ISO tanks
Construction of a logistics center (LC)
in the Khabarovsk Territory
Stage I
July 2022 - June 2023
* design of LC with the possibility of processing up to 120,000 TEU / year
Stage II
July 2023 - June 2025
* construction of a customs control point